Basement waterproofing needs a Performance Solution, because the NCC has no Deemed-to-Satisfy path below ground.

Let us explain. Above ground, a membrane can be designed by following a referenced Australian Standard. Below ground there is no such standard. The code tells you the result it wants and stops there, so the design has to be proven against the Performance Requirement.

The NCC's Deemed-to-Satisfy provisions for waterproofing cover roofs, balconies and podiums, and they cover damp-proofing of walls and floors on the ground. None of them covers a wall or slab holding back wet ground. AS 4654, the membrane standard the code refers to, says in its own scope that it is not for structures below ground level. BS 8102, the standard basements are actually designed to, is not referenced by the NCC. With no Deemed-to-Satisfy route available, a basement complies by a Performance Solution.

What the NCC covers, and where it stops

Clause numbers below are NCC 2022 Volume One, Part F1.

Why following BS 8102 is not enough on its own

Use, grade and water table: what BS 8102 asks for

BS 8102 does not start with a product. It starts with what the space is for, and works forward from there in five steps.

1UseWhat is each spaceused for?2GradeHow dry does ithave to be?3Water tableHigh, low orvariable?4ProtectionType A, B, Cor combined5ProofDoes it satisfyF1P4?
The order a basement waterproofing design is worked through. Each step sets the next.

Steps 1 and 2: the use sets the grade

Table 2 of BS 8102:2022 defines four grades of performance. The grade is chosen for each space by its use and agreed with the client at the start, because the internal finishes and contents decide how much water, if any, can be tolerated.

GradeWhat is toleratedWhere it typically fits
1aSeepage and damp areas, where they do not affect the use. Internal drainage may be needed to deal with the seepage.Car parks, plant areas
1bNo seepage. Damp areas are tolerable.Car parks, general stores
2No seepage. Dampness from condensation only, with water vapour managed.Plant rooms with electrical equipment, workshops
3No water ingress and no damp areas. Ventilation, dehumidification or air conditioning to suit the use.Habitable rooms, offices, archives

The third column is how the grades are usually applied. The standard defines the performance and leaves the choice to the design team and the client. It also says different parts of the same basement can need different grades, and that each must be identified in the design.

Storage cagesGrade 1bPlant and switch roomsGrade 2OfficeGrade 3Lift pitGrade 1bCarparkGrade 1a1a: seepage tolerable1b: no seepage, damp OK2: no seepage, vapour managed3: fully dry
An example basement level. One structure, four grades, each set by what the space holds.

Step 3: the water table

The classification comes from the geotechnical report and is tested against the deepest part of the structure. Clay is not free-draining, so a low reading in clay does not make the site Low.

Building aboveGround levelBasement 1Basement 2Lift pitUnderside of slab:above the waterGroundwater levelUnderside of lift pit: below the water.The basement is classified HIGH.
The general slab is above the groundwater, but the lift pit is not. The pit governs.

Step 4: the type of protection

Type A: barrierwet groundmembrane onthe outsideType B: integralwet groundwaterstopat the jointwater-resistingconcreteType C: drainedwet groundpumpdrained cavityand inner wall
The three types of protection in BS 8102. Type A keeps water off the structure, Type B makes the structure itself the barrier, and Type C collects the water that gets through and pumps it away.

What the Performance Solution has to show

Spend the money where the water gets in

The aim is the most protection against water penetration for the money spent. That means finding the place water is most likely to enter, and making sure the protection being paid for actually reaches it.

critical junctionag drainwet ground✗ Drain above the junctionInvert above the top ofthe slab. Water is loweredonly to the drain, so it stillstands against the joint.critical junctionag drainwet ground✓ Drain below the junction45°Invert below the top ofthe slab, and outside a 45°line from under the slab.The joint stays out of water.
The same ag drain at two levels. Both relieve pressure on the wall. For water penetration, the one above the junction is useless.

A worked example: how the evaluation runs

This is an illustrative example, not a design. Every basement is assessed on its own geotechnical report and drawings.

The building. A two-level basement under an apartment building. The perimeter is shotcrete with a concrete liner wall inside it. The geotechnical report measures groundwater 0.8 m below the underside of the basement slab, in clay. The lift pit is 1.4 m deeper than the slab.

  1. Use. Carpark, storage cages, plant and switch rooms, a building manager's office and a lift pit.
  2. Grade. Carpark 1a, storage and lift pit 1b, plant and switch rooms 2, office 3, as on the plan above.
  3. Water table. The slab is above the measured water, but the lift pit is 0.6 m below it and the ground is clay. The classification is High.
  4. Protection. Combined. The liner wall and slab are water-resisting concrete with a waterstop at every joint (Type B). The space between the shotcrete and the liner wall is drained to a perimeter drain and pump pit (Type C), with the drain set below the wall-to-slab joint. The lift pit, which sits in the water, has a pre-applied barrier under and around it, continuous with the wall system (Type A with Type B). The office is lined and ventilated to reach Grade 3.
  5. Proof. Each part of the requirement is answered with evidence, as below.
1Wall faceWater arrives atthe retained wall2DrainageSheet or stripdrains behind liner3PerimeterDrain at the toeof the wall4Pump pitDuty and standbypumps, alarm5Rising mainSized pipe toground level6DischargeNamed stormwaterconnection
In a drained design the report follows the water all the way out. Every leg is tied to a drawing and a revision.

How the design is tested against F1P4

What F1P4 requiresWhat the report shows
Moisture from the ground must not cause undue dampness or deterioration of building elementsConcrete grade and cover for each element. A waterstop at every construction joint, checked against the wall thickness. Drainage that stops water pressure building up behind the liner wall. A barrier where the structure sits below the water.
It must not cause unhealthy or dangerous conditions, or loss of amenity for occupantsThe grade achieved in each space against the grade its use needs. Expected seepage against pump capacity, with the standby pump able to carry the duty alone. An alarm, and the storage volume available if the power fails.
Comparison with Deemed-to-SatisfyWhat a damp-proof course and an under-slab vapour barrier would deliver, set against what the design delivers under water pressure.
Conditions of the solutionInspection hold points: before each pour, at waterstop installation and before backfilling. A maintenance schedule for the pumps and drains. A review if the ground conditions found on site are worse than the report assumed.

The conclusion is an engineer's opinion, with reasons, that the design meets F1P4. That is expert judgement under NCC A2G2, supported by the comparison.

What we find when there is no Performance Solution

Below ground there is no access to fix any of this once the excavation is backfilled. The Performance Solution is where these decisions are made on paper, before the concrete is poured.

Houses, and the newer code

Common questions

Is BS 8102 mandatory in Australia?

No. It is a British Standard and the NCC does not reference it. It is used because Australia has no standard of its own for below-ground waterproofing, and a Performance Solution is how it is brought into the compliance pathway.

The basement is only a carpark. Does it still need one?

Yes. An enclosed, mechanically ventilated carpark is still part of the building and still has to meet the requirement for moisture from the ground. A carpark is graded to tolerate some seepage, which makes the design simpler, but the grade, the drainage and the discharge still have to be shown. Lift pits, plant rooms and storage inside the carpark are graded separately.

What do you need from us to prepare it?

The geotechnical report, the architectural set-out plans, the structural drawings with the concrete grades and pour sequence, and the stormwater or hydraulic drawings showing where the water is discharged.

What if there is no geotechnical report?

We ask for one first. If it cannot be produced, the design assumes a high water table, the report says the classification is assumed and not measured, and a site investigation before construction is made a condition.

The membrane has a warranty and a product certificate. Is that not enough?

A certificate covers the product. It does not cover the water table on your site, the joints in your structure or where the water is discharged. The Performance Solution covers the building.

When should it be done?

At design stage, with the structural and stormwater drawings, and before the construction certificate. The choices it makes change the structure: concrete grade, waterstops, hobs, drains and pump pits.

What does it cost and how long does it take?

It depends on the number of basement levels and the ground conditions. Indicative fee bands and turnaround are on our NCC Performance Solution page, and every project is quoted on its own brief.

Basement on the drawings and no waterproofing design?

Send the address, the geotechnical report and the structural and stormwater drawings. We will tell you what the design needs, and come back with a scope and a fixed fee.

Need a Performance Solution report?
Excelo Consulting Engineers · Sydney · Melbourne · Gold Coast
NCC Performance Solutions →
Services
Compliance & Investigations
Resources