The NCC's Deemed-to-Satisfy provisions for waterproofing cover roofs, balconies and podiums, and they cover damp-proofing of walls and floors on the ground. None of them covers a wall or slab holding back wet ground. AS 4654, the membrane standard the code refers to, says in its own scope that it is not for structures below ground level. BS 8102, the standard basements are actually designed to, is not referenced by the NCC. With no Deemed-to-Satisfy route available, a basement complies by a Performance Solution.
What the NCC covers, and where it stops
Clause numbers below are NCC 2022 Volume One, Part F1.
- External membranes: F1D5. A roof, balcony, podium or similar horizontal surface gets a membrane with materials to AS 4654.1, designed and installed to AS 4654.2. A basement wall or a slab on wet ground is none of those.
- AS 4654 rules itself out. Its title is membranes for external above-ground use, and its scope states that it is not intended for structures below ground level.
- Damp-proofing: F1D6. A damp-proof course that stops moisture rising into walls and floor framing. It deals with capillary rise, not with water standing against a wall.
- Floors on the ground: F1D7. A damp-proofing membrane under the slab to AS 2870. That is a vapour barrier for a residential slab. It has no rating for water under pressure, and AS 2870 is not a basement standard.
- What is left is the requirement itself: F1P4. Moisture from the ground must not cause undue dampness or deterioration of building elements, or unhealthy or dangerous conditions or loss of amenity for the occupants.
Why following BS 8102 is not enough on its own
- It is the right standard. BS 8102:2022 is the recognised framework for protecting below-ground structures against water. It grades each space by its use, classifies the water table, and sets out the three types of protection.
- It is not a referenced document. The NCC does not call it up, so a design to BS 8102 is not a Deemed-to-Satisfy Solution, however good it is.
- The Performance Solution is what connects the two. It adopts BS 8102 as the design framework and shows, step by step, that the design meets F1P4.
Use, grade and water table: what BS 8102 asks for
BS 8102 does not start with a product. It starts with what the space is for, and works forward from there in five steps.
Steps 1 and 2: the use sets the grade
Table 2 of BS 8102:2022 defines four grades of performance. The grade is chosen for each space by its use and agreed with the client at the start, because the internal finishes and contents decide how much water, if any, can be tolerated.
| Grade | What is tolerated | Where it typically fits |
|---|---|---|
| 1a | Seepage and damp areas, where they do not affect the use. Internal drainage may be needed to deal with the seepage. | Car parks, plant areas |
| 1b | No seepage. Damp areas are tolerable. | Car parks, general stores |
| 2 | No seepage. Dampness from condensation only, with water vapour managed. | Plant rooms with electrical equipment, workshops |
| 3 | No water ingress and no damp areas. Ventilation, dehumidification or air conditioning to suit the use. | Habitable rooms, offices, archives |
The third column is how the grades are usually applied. The standard defines the performance and leaves the choice to the design team and the client. It also says different parts of the same basement can need different grades, and that each must be identified in the design.
Step 3: the water table
- High. The water table, or a perched water table, is permanently above the underside of the base slab.
- Low. It is permanently below the underside of the base slab. This classification only applies to free-draining ground.
- Variable. It fluctuates.
The classification comes from the geotechnical report and is tested against the deepest part of the structure. Clay is not free-draining, so a low reading in clay does not make the site Low.
Step 4: the type of protection
- Which types are acceptable depends on the water table. Table 1 of the standard sets this out, including extra requirements for a piled wall.
- Combined protection. Where the risk is high, or the consequence of a leak is too great, the standard calls for two types together, chosen so they do not fail for the same reason.
- With a high water table it points to combined protection, maintained sub-surface drainage, a fully bonded barrier and lower-permeability concrete.
What the Performance Solution has to show
- The requirement and the method. F1P4, assessed under NCC A2G2 by expert judgement, with a comparison against the Deemed-to-Satisfy damp-proofing provisions.
- The water table, from the geotechnical report. High, low or variable, tested against the underside of the deepest structure, which is usually a lift pit or pump pit and not the general slab.
- A grade for each space. A ventilated carpark can accept some seepage. A switchroom, lift pit or office inside the same basement cannot. One grade for the whole basement is almost always wrong.
- The type of protection. Type A is a barrier membrane, Type B is water-resisting concrete with waterstops at every joint, and Type C is a drained cavity with collection and pumps. Most basements combine two.
- Drained or sealed. A drained design accepts water at the structure and removes it. A sealed design keeps it out, and every joint carries that duty alone. The report picks one and every detail follows it.
- Every joint and penetration. Wall bases, wall-to-slab junctions, pit walls, the buried deck outside the building line and each service penetration, with the waterstop named and checked against the wall thickness.
- Where the water goes. In a drained basement the path is followed from the retained face to the perimeter drain, the pump tank, the rising main and the point of discharge, with the pump capacity checked against the expected seepage.
- Conditions. Inspection hold points during construction, and the maintenance the pumps and drains need for the life of the building.
Spend the money where the water gets in
The aim is the most protection against water penetration for the money spent. That means finding the place water is most likely to enter, and making sure the protection being paid for actually reaches it.
- The critical junction. The joint between the wall and the slab at the base of the wall. It is a construction joint, it is the lowest point of the wall, and it is where the water pressure is greatest.
- What we see very often on structural plans. An ag drain behind the wall, set above that junction.
- Why it is drawn there. The structural design is concerned with hydrostatic pressure on the wall. An ag drain part-way up the wall relieves that pressure, so for the structure it has done its job.
- Why that is not waterproofing. For water penetration, an ag drain installed above the critical junction is useless. A drain lowers the water only to its own level. Below it the ground stays saturated, so water still stands against the joint, at the place it is most likely to get in.
- What BS 8102 says. Clause 6.4 puts the drain outside the structure, beside the wall footing, falling to an outlet below the level of the lowest slab. Its Figure 5 marks a drain with its invert above the top of the floor slab as an incorrect position, because water pressure can build on the structure and get in through any defect. The drain is also kept outside a 45 degree line from the underside of the slab, so it does not undermine the footing.
- What the Performance Solution checks. The invert level of the ag drain against the level of the junction, on the structural drawings. Lowering the drain usually costs very little at design stage, and it is the difference between a drain that only relieves pressure and one that also keeps water off the joint.
A worked example: how the evaluation runs
This is an illustrative example, not a design. Every basement is assessed on its own geotechnical report and drawings.
The building. A two-level basement under an apartment building. The perimeter is shotcrete with a concrete liner wall inside it. The geotechnical report measures groundwater 0.8 m below the underside of the basement slab, in clay. The lift pit is 1.4 m deeper than the slab.
- Use. Carpark, storage cages, plant and switch rooms, a building manager's office and a lift pit.
- Grade. Carpark 1a, storage and lift pit 1b, plant and switch rooms 2, office 3, as on the plan above.
- Water table. The slab is above the measured water, but the lift pit is 0.6 m below it and the ground is clay. The classification is High.
- Protection. Combined. The liner wall and slab are water-resisting concrete with a waterstop at every joint (Type B). The space between the shotcrete and the liner wall is drained to a perimeter drain and pump pit (Type C), with the drain set below the wall-to-slab joint. The lift pit, which sits in the water, has a pre-applied barrier under and around it, continuous with the wall system (Type A with Type B). The office is lined and ventilated to reach Grade 3.
- Proof. Each part of the requirement is answered with evidence, as below.
How the design is tested against F1P4
| What F1P4 requires | What the report shows |
|---|---|
| Moisture from the ground must not cause undue dampness or deterioration of building elements | Concrete grade and cover for each element. A waterstop at every construction joint, checked against the wall thickness. Drainage that stops water pressure building up behind the liner wall. A barrier where the structure sits below the water. |
| It must not cause unhealthy or dangerous conditions, or loss of amenity for occupants | The grade achieved in each space against the grade its use needs. Expected seepage against pump capacity, with the standby pump able to carry the duty alone. An alarm, and the storage volume available if the power fails. |
| Comparison with Deemed-to-Satisfy | What a damp-proof course and an under-slab vapour barrier would deliver, set against what the design delivers under water pressure. |
| Conditions of the solution | Inspection hold points: before each pour, at waterstop installation and before backfilling. A maintenance schedule for the pumps and drains. A review if the ground conditions found on site are worse than the report assumed. |
The conclusion is an engineer's opinion, with reasons, that the design meets F1P4. That is expert judgement under NCC A2G2, supported by the comparison.
What we find when there is no Performance Solution
- A product chosen from the brochure. A membrane sold for below-ground use whose data sheet excludes submerged or below-water-table conditions.
- A water table that was assumed. Taken from the suburb, a neighbouring job, or a geotechnical report written for a different scheme.
- A drained design sealed at the slab junction. The gap between wall and slab is the path the water takes to the drain. Lap a membrane across it and the drainage the design relies on is closed off.
- An ag drain set above the wall-to-slab junction. Placed to relieve pressure on the wall. Useless for water penetration, because the joint still sits in water.
- A perimeter drain or hob deleted between drawing revisions. Nobody checks what it was doing for the waterproofing.
- Strip drains left off the shotcrete. Recommended in the geotechnical report, then dropped from the drawings without anyone agreeing to it.
Below ground there is no access to fix any of this once the excavation is backfilled. The Performance Solution is where these decisions are made on paper, before the concrete is poured.
Houses, and the newer code
- Houses. NCC Volume Two has the same gap. The requirement is H2P3, rising damp, and the Housing Provisions cover damp-proof courses and vapour barriers, not a habitable room cut into a slope.
- NCC 2025. Part F1 is renumbered: external membranes move to F1D7 and damp-proofing to F1D8 and F1D9. No below-ground provision is added, so the position is the same. The report cites the edition that applies to your project.
- Class 2 buildings in NSW. Waterproofing is a building element under the Design and Building Practitioners Act, so the basement waterproofing design is also a regulated design and is declared by a registered design practitioner. See who declares the waterproofing design.
Common questions
Is BS 8102 mandatory in Australia?
No. It is a British Standard and the NCC does not reference it. It is used because Australia has no standard of its own for below-ground waterproofing, and a Performance Solution is how it is brought into the compliance pathway.
The basement is only a carpark. Does it still need one?
Yes. An enclosed, mechanically ventilated carpark is still part of the building and still has to meet the requirement for moisture from the ground. A carpark is graded to tolerate some seepage, which makes the design simpler, but the grade, the drainage and the discharge still have to be shown. Lift pits, plant rooms and storage inside the carpark are graded separately.
What do you need from us to prepare it?
The geotechnical report, the architectural set-out plans, the structural drawings with the concrete grades and pour sequence, and the stormwater or hydraulic drawings showing where the water is discharged.
What if there is no geotechnical report?
We ask for one first. If it cannot be produced, the design assumes a high water table, the report says the classification is assumed and not measured, and a site investigation before construction is made a condition.
The membrane has a warranty and a product certificate. Is that not enough?
A certificate covers the product. It does not cover the water table on your site, the joints in your structure or where the water is discharged. The Performance Solution covers the building.
When should it be done?
At design stage, with the structural and stormwater drawings, and before the construction certificate. The choices it makes change the structure: concrete grade, waterstops, hobs, drains and pump pits.
What does it cost and how long does it take?
It depends on the number of basement levels and the ground conditions. Indicative fee bands and turnaround are on our NCC Performance Solution page, and every project is quoted on its own brief.
Basement on the drawings and no waterproofing design?
Send the address, the geotechnical report and the structural and stormwater drawings. We will tell you what the design needs, and come back with a scope and a fixed fee.